2019K0147 In Public Review ULURP

2959 Avenue Y Rezoning

Brooklyn · Yeshivat Or Hatorah

A zoning map amendment from R5 to R7D and a zoning text amendment to map a Mandatory Inclusionary Housing Area (ZR Appendix F) to facilitate a new seven-story, 79,945 square-foot building including 43,075 s.f. of residential space (38 units, 11 of which will be income-restricted) and 35,302 s.f. of community facility space, are being sought by private applicant Yeshivat Or HaTorah, at 2959 Avenue Y in Sheepshead Bay, Community District 15, Brooklyn.

Public review steps

  1. Completed · Thu, Mar 14, 2024 → Fri, Mar 15, 2024
    Land Use Application Filed
  2. Completed · Fri, Jul 23, 2021 → Tue, Aug 17, 2021
    Land Use Fee Paid
  3. Completed · Wed, Nov 19, 2025 → Wed, Nov 19, 2025
    Environmental Assessment Statement Filed
  4. Completed · Mon, Jul 3, 2023 → Fri, Aug 4, 2023
    CEQR Fee Paid
  5. Completed · Wed, Sep 9, 2026 → Tue, Sep 15, 2026
    Application Reviewed at City Planning Commission Review Session
    A "Review Session" milestone signifies that the application has been sent to the City Planning Commission (CPC) and is ready for review. The "Review" milestone represents the period of time (up to 60 days) that the CPC reviews the application before their vote.
  6. Completed · Fri, Sep 18, 2026 → Wed, Oct 28, 2026
    Community Board Review
    The Community Board has 60 days from the time of referral (nine days after certification) to hold a hearing and issue a recommendation.
  7. In Progress · Thu, Oct 29, 2026 → Thu, Nov 26, 2026
    Borough President Review
    The Borough President has 30 days after the Community Board issues a recommendation to review the application and issue a recommendation.
  8. Not Started → Fri, Nov 27, 2026
    Review Session - Pre-Hearing Review / Post Referral
  9. Not Started → Sat, Nov 28, 2026
    City Planning Commission Review
    The City Planning Commission has 60 days after the Borough President issues a recommendation to hold a hearing and vote on an application.
  10. Not Started → Fri, Dec 4, 2026
    Post Hearing Follow-Up / Future Votes
  11. Not Started → Mon, Dec 7, 2026
    City Planning Commission Vote
  12. Not Started → Wed, Apr 28, 2027
    City Council Review
    The City Council has 50 days from receiving the City Planning Commission report to call up the application, hold a hearing and vote on the application.
  13. Not Started → Tue, Sep 8, 2026
    Request for Appeals Board Review
    The Applicant and the Affordable Housing Appeals Board have five days to review the City Council’s decision and request a call up or appeal.
  14. Not Started → Wed, Sep 23, 2026
    Appeals Board Review
    The Affordable Housing Appeals Board has 15 days after the call up or appeal to restore the City Planning Commission action, partially restore the City Planning Commission action, or sustain the City Council action.