2021Q0168 In Public Review ULURP
189-10 Northern Boulevard Commercial Overlay
Queens · PRINCE ST 606 LLC
A zoning map amendment to establish a C2-3 commercial overlay on an existing R3-2 district, and reduce the depth of an existing R3X district, to facilitate a new three story, 30,190-square-foot mixed-use (commercial/community facility) building, including 9,661 sf of commercial space and 5,202 sf of community facility space, is being sought by private applicant, PRINCE ST 606 LLC, at 189-10 Northern Boulevard in the Auburndale neighborhood, Community District 11, Queens.
Public review steps
-
Completed · Tue, Apr 26, 2022 → Tue, Apr 26, 2022Land Use Application Filed
-
Completed · Tue, Nov 23, 2021 → Thu, Dec 9, 2021Land Use Fee Paid
-
Completed · Thu, Feb 17, 2022 → Mon, Aug 15, 2022Environmental Assessment Statement Filed
-
Completed · Wed, Dec 28, 2022 → Wed, Dec 28, 2022CEQR Fee Paid
-
Completed · Wed, Dec 21, 2022 → Thu, Jan 12, 2023Application Reviewed at City Planning Commission Review SessionA "Review Session" milestone signifies that the application has been sent to the City Planning Commission (CPC) and is ready for review. The "Review" milestone represents the period of time (up to 60 days) that the CPC reviews the application before their vote.
-
Completed · Thu, Jan 12, 2023 → Tue, Mar 7, 2023Community Board ReviewThe Community Board has 60 days from the time of referral (nine days after certification) to hold a hearing and issue a recommendation.
-
Completed · Wed, Mar 8, 2023 → Thu, Apr 6, 2023Borough President ReviewThe Borough President has 30 days after the Community Board issues a recommendation to review the application and issue a recommendation.
-
Completed · Wed, Mar 29, 2023 → Mon, Apr 10, 2023Review Session - Pre-Hearing Review / Post Referral
-
Completed · Mon, Apr 10, 2023 → Wed, Apr 12, 2023City Planning Commission ReviewThe City Planning Commission has 60 days after the Borough President issues a recommendation to hold a hearing and vote on an application.
-
Completed · Thu, Apr 13, 2023 → Mon, May 8, 2023Post Hearing Follow-Up / Future Votes
-
Completed · Tue, May 9, 2023 → Wed, May 10, 2023City Planning Commission Vote