2023K0148 In Public Review ULURP
460 Troutman Street
Brooklyn · Aron's Manufacturing Corporation
A zoning map amendment from M1-1 to M1-4A to facilitate the enlargement of an existing one-story manufacturing building to expand business operations in a 6-story, 93,000 SF manufacturing and commercial building is being sought by Aron's Manufacturing Corporation at 460 Troutman Street in Bushwick, Community District 4, Brooklyn.
Public review steps
-
Completed · Mon, Mar 11, 2024 → Wed, Aug 7, 2024Land Use Application Filed
-
Completed · Tue, Feb 6, 2024 → Tue, Feb 13, 2024Land Use Fee Paid
-
Completed · Tue, Jul 14, 2026 → Fri, Jul 24, 2026Environmental Assessment Statement Filed
-
Completed · Tue, Sep 5, 2023 → Wed, Sep 6, 2023CEQR Fee Paid
-
Completed · Mon, Aug 3, 2026 → Tue, Sep 1, 2026Application Reviewed at City Planning Commission Review SessionA "Review Session" milestone signifies that the application has been sent to the City Planning Commission (CPC) and is ready for review. The "Review" milestone represents the period of time (up to 60 days) that the CPC reviews the application before their vote.
-
Completed · Wed, Sep 2, 2026 → Fri, Oct 30, 2026Community Board ReviewThe Community Board has 60 days from the time of referral (nine days after certification) to hold a hearing and issue a recommendation.
-
In Progress · Sat, Oct 31, 2026 → Mon, Nov 30, 2026Borough President ReviewThe Borough President has 30 days after the Community Board issues a recommendation to review the application and issue a recommendation.
-
Not Started → Fri, Dec 18, 2026Review Session - Pre-Hearing Review / Post Referral
-
Not Started → Mon, Dec 21, 2026City Planning Commission ReviewThe City Planning Commission has 60 days after the Borough President issues a recommendation to hold a hearing and vote on an application.
-
Not Started → Tue, Dec 29, 2026Post Hearing Follow-Up / Future Votes
-
Not Started → Fri, Jan 1, 2027City Planning Commission Vote
-
Not Started → Mon, Apr 5, 2027City Council ReviewThe City Council has 50 days from receiving the City Planning Commission report to call up the application, hold a hearing and vote on the application.
-
Not Started → Wed, Apr 7, 2027Mayoral ReviewThe Mayor has five days to review the City Councils decision and issue a veto.