Community boards › Land use › 2023K0231
2023K0231 In Public Review ULURP
150 Noll Street
Brooklyn · Noll Street Realty USA LLC
An application for a Zoning Map Amendment to map a C2-4 overlay in a R6 district to facilitate an active ground floor commercial use in a five-story mixed-use building with 73,852 zoning square feet including 994 zsf of community facility space, 17,859 zsf of commercial space, and 81 dwelling units is being sought by private applicant Noll Street Realty USA LLC in Bushwick, Community Board 4, Brooklyn.
Public review steps
-
Completed · Tue, Jan 27, 2026 → Mon, Feb 16, 2026Land Use Application Filed
-
Completed · Tue, Feb 17, 2026 → Tue, Feb 17, 2026Land Use Fee Paid
-
Completed · Fri, Apr 10, 2026 → Wed, Jun 10, 2026Environmental Assessment Statement Filed
-
Completed · Tue, Sep 23, 2025 → Mon, Sep 29, 2025CEQR Fee Paid
-
Completed · Wed, Jun 17, 2026 → Tue, Jun 23, 2026Application Reviewed at City Planning Commission Review SessionA "Review Session" milestone signifies that the application has been sent to the City Planning Commission (CPC) and is ready for review. The "Review" milestone represents the period of time (up to 60 days) that the CPC reviews the application before their vote.
-
Completed · Wed, Jun 24, 2026 → Mon, Sep 21, 2026Community Board ReviewThe Community Board has 60 days from the time of referral (nine days after certification) to hold a hearing and issue a recommendation.
-
Completed · Tue, Sep 22, 2026 → Thu, Oct 22, 2026Borough President ReviewThe Borough President has 30 days after the Community Board issues a recommendation to review the application and issue a recommendation.
-
Completed · Thu, Oct 22, 2026 → Mon, Oct 26, 2026Review Session - Pre-Hearing Review / Post Referral
-
Completed · Mon, Oct 26, 2026 → Wed, Oct 28, 2026City Planning Commission ReviewThe City Planning Commission has 60 days after the Borough President issues a recommendation to hold a hearing and vote on an application.
-
In Progress · Thu, Nov 5, 2026 → Mon, Nov 16, 2026Post Hearing Follow-Up / Future Votes
-
Not Started → Thu, Nov 19, 2026City Planning Commission Vote
-
Not Started → Tue, Jan 19, 2027City Council ReviewThe City Council has 50 days from receiving the City Planning Commission report to call up the application, hold a hearing and vote on the application.
-
Not Started → Mon, Jan 25, 2027Mayoral ReviewThe Mayor has five days to review the City Councils decision and issue a veto.