2023R0153 In Public Review Non-ULURP

Staten Island Mall Outparcels

Staten Island · GGP Staten Island Mall LLC

This is a private application submitted by GGP Staten Island Mall, LLC requesting several CPC Authorizations per ZR 36-022 to facilitate the development of seven (7) new retails pads totaling 41,300 square feet within an existing group parking facility, as well as Chair Certification per ZR 36-58 for cross access connections, in the Heartland Village neighborhood of Staten Island, Community District 2.

Public review steps

  1. Completed · Wed, Apr 16, 2025 → Tue, May 6, 2025
    Land Use Application Filed
  2. Not Started → Sun, Nov 29, 2026
    Land Use Application Filed
  3. Completed · Tue, Dec 24, 2024 → Thu, Jan 9, 2025
    Land Use Fee Paid
  4. Completed · Thu, Aug 14, 2025 → Mon, Aug 25, 2025
    Environmental Assessment Statement Filed
  5. Completed · Tue, Oct 15, 2024 → Thu, Oct 17, 2024
    CEQR Fee Paid
  6. Completed · Wed, Nov 12, 2025 → Thu, Mar 19, 2026
    Community Board Review
    The City Planning Commission refers to the Community Board for 30, 45 or 60 days.
  7. In Progress · Sat, Mar 21, 2026 → Tue, Jun 16, 2026
    Review Session - Pre-Hearing Review / Post Referral
  8. Not Started → Sat, Jan 23, 2027
    Post Hearing Follow-Up / Future Votes
  9. Not Started → Tue, Jan 26, 2027
    City Planning Commission Vote
  10. Not Started → Sat, Feb 6, 2027
    Approval Letter Sent to Responsible Agency
    For many non-ULURP actions this is the final action and record of the decision.