2024M0267 In Public Review Non-ULURP

625 Madison Avenue

Manhattan · 625 Mad Realty LLC

A private applicant, 625 Mad Realty LLC, is seeking MTA transit improvement bonus authorizations (ZR 66-511 and ZR 66-521) to facilitate the construction of an approximately 626,257-square-foot office tower at 625 Madison Avenue in the East Midtown neighborhood of Manhattan, Community District 5.

Public review steps

  1. Completed · Fri, Aug 14, 2026 → Mon, Aug 17, 2026
    Land Use Application Filed
  2. Completed → Fri, Aug 14, 2026
    Land Use Fee Paid
  3. Completed · Fri, Aug 7, 2026 → Tue, Aug 18, 2026
    Environmental Assessment Statement Filed
  4. Completed · Tue, Jun 16, 2026 → Tue, Jun 16, 2026
    CEQR Fee Paid
  5. Completed · Tue, Sep 1, 2026 → Wed, Oct 14, 2026
    Community Board Review
    The City Planning Commission refers to the Community Board for 30, 45 or 60 days.
  6. Completed · Wed, Oct 14, 2026 → Mon, Oct 26, 2026
    Review Session - Pre-Hearing Review / Post Referral
  7. In Progress · Thu, Nov 5, 2026 → Fri, Nov 20, 2026
    Post Hearing Follow-Up / Future Votes
  8. Not Started → Mon, Nov 23, 2026
    City Planning Commission Vote
  9. Not Started → Fri, Dec 4, 2026
    Approval Letter Sent to Responsible Agency
    For many non-ULURP actions this is the final action and record of the decision.