Civic Agendas NYC
Community boards › Land use › 2024R0332
2024R0332 In Public Review ULURP

5801 Amboy Road Commercial Overlay

Staten Island · Ed Rice

This is a private application, by 5801-14 Amboys LLC, seeking a Zoning Map Amendment to establish a new C2-2 commercial overlay on two lots in an R3X district within the Special South Richmond Development District (SRD) to facilitate the expansion of an existing Starbucks drive-through (Use Group VI). The proposed project area (Block 6896, Lots 50 & 53) is 22,055 square feet and within the Prince’s Bay neighborhood of Staten Island’s Community District 3.

Public review steps

  1. Completed · Thu, Mar 26, 2026 → Fri, Apr 17, 2026
    Land Use Application Filed
  2. Completed · Fri, Apr 17, 2026 → Mon, Apr 20, 2026
    Land Use Fee Paid
  3. Completed · Mon, Dec 1, 2025 → Wed, Dec 17, 2025
    Environmental Assessment Statement Filed
  4. Completed · Mon, Dec 22, 2025 → Mon, Dec 22, 2025
    CEQR Fee Paid
  5. Completed · Tue, Jul 14, 2026 → Tue, Aug 4, 2026
    Application Reviewed at City Planning Commission Review Session
    A "Review Session" milestone signifies that the application has been sent to the City Planning Commission (CPC) and is ready for review. The "Review" milestone represents the period of time (up to 60 days) that the CPC reviews the application before their vote.
  6. Completed · Wed, Aug 5, 2026 → Mon, Sep 28, 2026
    Community Board Review
    The Community Board has 60 days from the time of referral (nine days after certification) to hold a hearing and issue a recommendation.
  7. Completed · Tue, Sep 29, 2026 → Mon, Nov 2, 2026
    Borough President Review
    The Borough President has 30 days after the Community Board issues a recommendation to review the application and issue a recommendation.
  8. In Progress · Tue, Nov 3, 2026 → Thu, Nov 5, 2026
    Review Session - Pre-Hearing Review / Post Referral
  9. Not Started → Wed, Nov 11, 2026
    City Planning Commission Review
    The City Planning Commission has 60 days after the Borough President issues a recommendation to hold a hearing and vote on an application.
  10. Not Started → Thu, Nov 19, 2026
    Post Hearing Follow-Up / Future Votes
  11. Not Started → Sun, Nov 22, 2026
    City Planning Commission Vote
  12. Not Started → Mon, Jan 18, 2027
    City Council Review
    The City Council has 50 days from receiving the City Planning Commission report to call up the application, hold a hearing and vote on the application.
  13. Not Started → Sun, Jan 24, 2027
    Mayoral Review
    The Mayor has five days to review the City Councils decision and issue a veto.
  14. Not Started → Thu, Feb 4, 2027
    Approval Letter Sent to Responsible Agency