2025K0497 In Public Review ULURP

Con Edison Permanent Easement Gateway Microtunnel

Brooklyn · DCAS - NYC Department of Citywide Administrative Services

An application by the Department of Citywide Administrative Services (DCAS) for disposition approval of a permanent subsurface easement to allow construction of microtunnel and feeders by Consolidated Edison at 209 York Street (Block 56, part of Lot 7) in Community District 2, Brooklyn.

Public review steps

  1. Completed · Wed, Nov 19, 2025 → Mon, Mar 30, 2026
    Land Use Application Filed
  2. Completed · Mon, Apr 20, 2026 → Tue, May 19, 2026
    Application Reviewed at City Planning Commission Review Session
    A "Review Session" milestone signifies that the application has been sent to the City Planning Commission (CPC) and is ready for review. The "Review" milestone represents the period of time (up to 60 days) that the CPC reviews the application before their vote.
  3. Completed · Wed, May 20, 2026 → Mon, Jul 6, 2026
    Community Board Review
    The Community Board has 60 days from the time of referral (nine days after certification) to hold a hearing and issue a recommendation.
  4. Completed · Tue, Jul 7, 2026 → Wed, Aug 5, 2026
    Borough President Review
    The Borough President has 30 days after the Community Board issues a recommendation to review the application and issue a recommendation.
  5. Completed · Thu, Aug 6, 2026 → Mon, Aug 10, 2026
    Review Session - Pre-Hearing Review / Post Referral
  6. Completed · Mon, Aug 10, 2026 → Wed, Aug 12, 2026
    City Planning Commission Review
    The City Planning Commission has 60 days after the Borough President issues a recommendation to hold a hearing and vote on an application.