Civic Agendas NYC
Community boards › Land use › 2025M0338
2025M0338 In Public Review ULURP

Imperial Theatre Text Amendment

Manhattan · Imperial Theater LLC

A zoning text amendment to ZR Sections 81-744 and 81-745 and a special permit pursuant to ZR 81-745 to facilitate a floor area bonus for the rehabilitation of an existing listed theater is being sought by private applicant at 249 West 45th Street in the Theater District, Community District 5, Manhattan.

Public review steps

  1. Completed · Mon, Jun 8, 2026 → Tue, Jun 30, 2026
    Land Use Application Filed
  2. Completed · Wed, Feb 25, 2026 → Tue, Mar 3, 2026
    Land Use Fee Paid
  3. Completed · Tue, Dec 23, 2025 → Mon, Jun 29, 2026
    Environmental Assessment Statement Filed
  4. Completed · Tue, Jun 30, 2026 → Tue, Jun 30, 2026
    CEQR Fee Paid
  5. Completed · Wed, Sep 23, 2026 → Fri, Oct 2, 2026
    Application Reviewed at City Planning Commission Review Session
    A "Review Session" milestone signifies that the application has been sent to the City Planning Commission (CPC) and is ready for review. The "Review" milestone represents the period of time (up to 60 days) that the CPC reviews the application before their vote.
  6. In Progress · Fri, Oct 2, 2026 → Mon, Nov 30, 2026
    Community Board Review
    The Community Board has 60 days from the time of referral (nine days after certification) to hold a hearing and issue a recommendation.
  7. Not Started → Mon, Jan 4, 2027
    Borough President Review
    The Borough President has 30 days after the Community Board issues a recommendation to review the application and issue a recommendation.
  8. Not Started → Mon, Jan 11, 2027
    Review Session - Pre-Hearing Review / Post Referral
  9. Not Started → Thu, Jan 14, 2027
    City Planning Commission Review
    The City Planning Commission has 60 days after the Borough President issues a recommendation to hold a hearing and vote on an application.
  10. Not Started → Fri, Jan 22, 2027
    Post Hearing Follow-Up / Future Votes
  11. Not Started → Mon, Jan 25, 2027
    City Planning Commission Vote
  12. Not Started → Fri, Mar 26, 2027
    City Council Review
    The City Council has 50 days from receiving the City Planning Commission report to call up the application, hold a hearing and vote on the application.
  13. Not Started → Thu, Apr 1, 2027
    Mayoral Review
    The Mayor has five days to review the City Councils decision and issue a veto.
  14. Not Started → Mon, Apr 12, 2027
    Approval Letter Sent to Responsible Agency