Civic Agendas NYC
Community boards › Land use › 2025Q0124
2025Q0124 In Public Review ULURP

Steinway Street and 34th Avenue Rezoning

Queens · Frank St. Jacques

A zoning map amendment from M1-1 and C4-2A to C4-5X and M1-1A/R7A and a zoning text amendment to Appendix F to map MIH to facilitate two new mixed-use buildings, 12 and 9 stories, containing 278,800 zoning sq ft, which includes 243 dwelling units of which 61 would be income restricted, 45,700 sq ft of commercial, and 28,400 sq ft of community facility, is being sought by Schuman LLC at 34-02 Steinway Street in Astoria, Community District 1, Queens.

Public review steps

  1. Completed · Mon, Oct 6, 2025 → Wed, Jul 15, 2026
    Land Use Application Filed
  2. Completed · Thu, Sep 3, 2026 → Thu, Sep 3, 2026
    Land Use Fee Paid
  3. Completed · Fri, Jan 23, 2026 → Thu, Feb 26, 2026
    Environmental Assessment Statement Filed
  4. Completed · Fri, Feb 27, 2026 → Mon, Mar 2, 2026
    CEQR Fee Paid
  5. Completed · Tue, Sep 29, 2026 → Tue, Nov 3, 2026
    Application Reviewed at City Planning Commission Review Session
    A "Review Session" milestone signifies that the application has been sent to the City Planning Commission (CPC) and is ready for review. The "Review" milestone represents the period of time (up to 60 days) that the CPC reviews the application before their vote.
  6. In Progress · Wed, Nov 4, 2026 → Mon, Jan 4, 2027
    Community Board Review
    The Community Board has 60 days from the time of referral (nine days after certification) to hold a hearing and issue a recommendation.
  7. Not Started → Mon, Feb 8, 2027
    Borough President Review
    The Borough President has 30 days after the Community Board issues a recommendation to review the application and issue a recommendation.
  8. Not Started → Mon, Feb 15, 2027
    Review Session - Pre-Hearing Review / Post Referral
  9. Not Started → Thu, Feb 18, 2027
    City Planning Commission Review
    The City Planning Commission has 60 days after the Borough President issues a recommendation to hold a hearing and vote on an application.
  10. Not Started → Fri, Feb 26, 2027
    Post Hearing Follow-Up / Future Votes
  11. Not Started → Mon, Mar 1, 2027
    City Planning Commission Vote
  12. Not Started → Thu, May 13, 2027
    City Council Review
    The City Council has 50 days from receiving the City Planning Commission report to call up the application, hold a hearing and vote on the application.
  13. Not Started → Thu, May 20, 2027
    Request for Appeals Board Review
    The Applicant and the Affordable Housing Appeals Board have five days to review the City Council’s decision and request a call up or appeal.
  14. Not Started → Fri, Jun 4, 2027
    Appeals Board Review
    The Affordable Housing Appeals Board has 15 days after the call up or appeal to restore the City Planning Commission action, partially restore the City Planning Commission action, or sustain the City Council action.